Weekly status: [Project or team]
Week of [date] · Prepared by [name]
Status: On track At risk Off track keep one
Summary:
Need from you:
See an example
Status: At risk
Summary: Beta moves from May 7 to May 14. The security review found two issues in the payments flow; both are fixed and in retest, and nothing else on the launch plan has moved.
Need from you: Dana, please approve moving the launch email to May 21 by Wednesday, so marketing can reschedule the send.
Milestones
Milestone | Due | Status | Note |
Done this week
Next week
Each with an owner and a day.
Risks and blockers
Risk or blocker | Impact | Owner | Next step |
Optional: Metrics
Metric | Last week | This week | Target |
Next report: [date]. Questions to [name or channel].